Pre-Construction and Post-Construction Land Drainage for the Maybole to Girvan 250mm dia. Reinforcement Pipeline
Location:
Between Maybole and Girvan, Ayrshire, Scotland
Date:
May to August 2011
Duration:
Pre-Con 5 weeks, Post-Con 5 weeks.
Equipment:
Mastenbroek 30/20, 360ยบ Excavator, 2 x LD1000 Tracked Stone Carts, Mastenbroek CT-12
Description:
DMJ Drainage were assigned to carry out both the Pre-Construction and Post-Construction Phase of the 15km Gas Pipeline that Land and Marine completed on behalf of Scottish Gas Networks. Due to the terrain, the majority of the drainage works were completed by the backhoe method. Although poor weather conditions played a big part, all Land Drainage works were completed to plan and within time and budget.